Lake River Corp. v. Carborundum

Lake River Corp. v. Carborundum

769 F.2d 1284 (7th Cir. 1985)

 

Posner, Circuit Judge.

This diversity suit between Lake River Corporation and Carborundum Company requires us to consider questions of Illinois commercial law, and in particular to explore the fuzzy line between penalty clauses and liquidated-damages clauses.

Carborundum manufactures “Ferro Carbo,” an abrasive powder used in making steel. To serve its midwestern customers better, Carborundum made a contract with Lake River by which the latter agreed to provide distribution services in its warehouse in Illinois. Lake River would receive Ferro Carbo in bulk from Carborundum, “bag” it, and ship the bagged produce to Carborundum’s customers. The Ferro Carbo would remain Carborundum’s property until delivered to the customers.

Carborundum insisted that Lake River install a new bagging system to handle the contract. In order to be sure of being able to recover the cost of the new system ($89,000) and make a profit of 20 percent of the contract price, Lake River insisted on the following minimum-quantity guarantee:

In consideration of the special equipment [i.e., the new bagging system] to be acquired and furnished by LAKE-RIVER for handling the product, CARBORUNDUM shall, during the initial three-year term of his Agreement, ship to LAKE-RIVER for bagging a minimum quantity of [22,500 tons]. If, at the end of the three-year term, this minimum quantity shall not have been shipped, LAKE-RIVER shall invoice CARBORUNDUM at the then prevailing rates for the difference between the quantity bagged and the minimum guaranteed.

If Carborundum had shipped the full minimum quantity that it guaranteed, it would have owed Lake River roughly $533,000 under the contract.

Question

Suppose Carborundum breaches one year into the contract by permanently ceasing to ship to Lake River any ferro carob.

(a) Lake River would still incur the expense of bagging and shipping the ferro carbo.

(b) Lake River would not incur the expense of bagging and shipping the ferro carbo.

Would incur

Incorrect. With no ferro carbo to bag and ship, Lake River would not incur the bagging and shipping costs. Bear this in mind as you read the rest of the case.

Would not incur

Correct. With no ferro carbo to bag and ship, Lake River would not incur the bagging and shipping costs. Bear this in mind as you read the rest of the case.

After the contract was signed in 1979, the demand for domestic steel, and with it the demand for Ferro Carbo, plummeted, and Carborundum failed to ship the guaranteed amount. When the contract expired late in 1982, Carborundum had shipped only 12,000 of the 22,500 tons it had guaranteed. Lake River had bagged the 12,000 tons and had billed Carborundum for this bagging, and Carborundum had paid, but by virtue of the formula in the minimum-guarantee clause Carborundum still owed Lake River $241,000-the contract price of $533,000 if the full amount of Ferro Carbo had been shipped, minus what Carborundum had paid for the bagging of the quantity it had shipped.

When Lake River demanded payment of this amount, Carborundum refused, on the ground that the formula imposed a penalty. At the time, Lake River had in its warehouse 500 tons of bagged Ferro Carbo, having a market value of $269,000, which it refused to release unless Carborundum paid the $241,000 due under the formula. Lake River did offer to sell the bagged product and place the proceeds in escrow until its dispute with Carborundum over the enforceability of the formula was resolved, but Carborundum rejected the offer and trucked in bagged Ferro Carbo from the East to serve its customers in Illinois, at an additional cost of $31,000.

Lake River brought this suit for $241,000, which it claims as liquidated damages. Carborundum counterclaimed for the value of the bagged Ferro Carbo when Lake River impounded it and the additional cost of serving the customers affected by the impounding. The theory of the counterclaim is that the impounding was a conversion, and not as Lake River contends the assertion of a lien. The district judge, after a bench trial, gave judgment for both parties. Carborundum ended up roughly $42,000 to the good: $269,000 + $31,000-$241,00-$17,000, the last figure representing prejudgment interest on Lake River’s damages. (We have rounded off all dollar figures to the nearest thousand.) Both parties have appealed.

The only issue that is not one of damages is whether Lake River had a valid lien on the bagged Ferro Carbo that it refused to ship to Carborundum’s customers-that, indeed, it holds in its warehouse to this day. Although Ferro Carbo does no deteriorate with age, the domestic steel industry remains in the doldrums and the product is worth less than it was in 1982 when Lake River first withheld it. If Lake River did not have a valid lien on the product, then it converted it, and must pay Carborundum the $269,000 that the Ferro Carbo was worth back then. . . .

[The court held there was no valid lien.]

The hardest issue in the case is whether the formula in the minimum-guarantee clause imposes a penalty for breach of contract or is merely an effort to liquidate damages. Deep as the hostility to penalty clauses runs in the common law, see Loyd, Penalties and Forfeitures, 29 Harv. L. Rev. 117 (1915), we still might be inclined to question, if we thought ourselves free to do so, whether a modern court should refuse to enforce a penalty clause where the signator is a substantial corporation, well able to avoid improvident commitments.

Question

A “substantial corporation” is a legally sophisticated entity that has sufficient bargaining power to “avoid improvident commitments,” so it if agrees to a “penalty clause,” the presumption should be that it judged the overall contract containing the clause to be a favorable one that it was rational to enter.

(a) True

Correct. So then why should a court refuse to enforce the clause? This is the question that concerns Judge Posner.

(b) False

Incorrect. So then why should a court refuse to enforce the clause? This is the question that concerns Judge Posner.

Penalty clauses provide an earnest of performance. The clause here enhanced Carborundum’s credibility in promising to ship the minimum amount guaranteed by showing that it was willing to pay the full contract price even if it failed to ship anything. On the other side it can be pointed out that by raising the cost of a breach of contract to the contract breaker, a penalty clause increases the risk to his other creditors; increases (what is the same thing and more, because bankruptcy imposes “deadweight” social costs) the risk of bankruptcy; and could amplify the business cycle by increasing the number of bankruptcies in bad times, which is when contracts are most likely to be broken. But since little effort is made to prevent businessmen from assuming risks, these reasons are no better than makeweights.

A better argument is that a penalty clause may discourage efficient as well as inefficient breaches of contract. Suppose a breach would cost the promisee $12,000 in actual damages but would yield the promisor $20,000 in additional profits. Then there would be a net social gain from breach. After being fully compensated for his loss the promissee would be no worse off than if the contract had been performed, while the promisor would be better off by $8,000. But now suppose the contract contains a penalty clause under which the promisor if he breaks his promise must pay the promisee $25,000. The promisor will be discouraged from breaking the contract, since $25,000, the penalty, is greater than $20,000, the profits of the breach; and a transaction that would have increased value will be forgone.

On this view, since compensatory damages should be sufficient to deter inefficient breaches (that is, breaches that cost the victim more than the gain to the contract breaker), penal damages could have no effect other than to deter some efficient breaches. But this overlooks the earlier point that the willingness to agree to a penalty clause is a way of making the promisor and his promise credible and may therefore be essential to inducing some value-maximizing contracts to be made. It also overlooks the more important point that the parties (always assuming they are fully competent) will, in deciding whether to include a penalty clause in their contract, weigh the gains against the costs–costs that include the possibility of discouraging an efficient breach somewhere down the road–and will include the clause only if the benefits exceed those costs as well as all other costs.

On this view the refusal to enforce penalty clauses is (at best) paternalistic–and it seems odd that courts should display parental solicitude for large corporations. But however this may be, we must be on guard to avoid importing our own ideas of sound public policy into an area where our proper judicial role is more than usually deferential. The responsibility for making innovations in the common law of Illinois rests with the courts of Illinois, and not with the federal courts in Illinois. And like every other state, Illinois, untroubled by academic skepticism of the wisdom of refusing to enforce penalty clauses against sophisticated promisors, see, e.g., Goetz & Scott, Liquidated Damages, Penalties and the Just Compensation Principle, 77 Colum. L. Rev. 554 (1977), continues steadfastly to insist on the distinction between penalties and liquidated damages. . .  . To be valid under Illinois law a liquidation of damages must be a reasonable estimate at the time of contracting of the likely damages from breach, and the need for estimation at that time must be shown by reference to the likely difficulty of measuring the actual damages from a breach of contract after the breach occurs. If damages would be easy to determine then, of if the estimate greatly exceeds a reasonable upper estimate of what the damages are likely to be, it is a penalty. . . .

The distinction between a penalty and liquidated damages is not an easy one to draw in practice but we are required to draw it and can give only limited weight to the district court’s determination. Whether a provision for damages is a penalty clause or a liquidated-damages clause is a question of law rather than fact, . . . , and unlike some courts of appeals we do not treat a determination by a federal district judge on an issue of state law as if it were a finding of fact, and reverse only if persuaded that clear error has occurred, though we give his determination respectful consideration. . . .

Mindful that Illinois courts resolve doubtful cases in favor of classification as a penalty, . . . , we conclude that the damage formula in this case is a penalty and not a liquidation of damages, because it is designed always to assure Lake River more than its actual damages. The formula–full contract price minus the amount already invoiced to Carborundum–is invariant to the gravity of the breach. When a contract specifies a single sum in damages for any and all breaches even though it is apparent that all are not of the same gravity, the specification is not a reasonable effort to estimate damages; and when in addition the fixed sum greatly exceeds the actual damages likely to be inflicted by a minor breach, its character as a penalty becomes unmistakable. . . . This case is within the gravitational field of these principles even though the minimum-guarantee clause does not fix a single sum as damages.

Suppose to begin with that the breach occurs the day after Lake River buys its new bagging system for $89,000 and before Carborundum ships any Ferro Carbo. Carborundum would owe Lake River $533,000. Since Lake River would have incurred at that point a total cost of only $89,000, its net gain from the breach would be $444,000. This is more than four times the profit of $107,000 (20 percent of the contract price of $533,000) that Lake River expected to make from the contract if it had been performed: a huge windfall.

Next suppose (as actually happened here) that breach occurs when 55 percent of the Ferro Carbo has been shipped. Lake River would already have received $293,000 from Carborundum. To see what its costs then would have been (as estimated at the time of contracting), first subtract Lake River’s anticipated profit on the contract of $107,000 from the total contract price of $533,000. The difference-Lake River’s total cost of performance-is $426,000. Of this, $89,000 is the cost of the new bagging system, a fixed cost. The rest ($426,000-$89,000=$337,000) presumably consists of variable costs that are roughly proportional to the amount of Ferro Carbo bagged; there is no indication of any other fixed costs. Assume, therefore, that if Lake River bagged 55 percent of the contractually agreed quantity, it incurred in doing so 55 percent of its variable costs, or $185,000. When this is added to the cost of the new bagging system, assumed for the moment to be worthless except in connection with the contract, the total cost of performance to Lake River is $274,000. Hence a breach that occurred after 55 percent of contractual performance was complete would be expected to yield Lake River a modest profit of $19,000 ($293,000-$274,000). But now add the “liquidated damages” of $241,000 that Lake River claims, and the result is a total gain from the breach of $260,000, which is almost two and a half times the profit that Lake River expected to gain if there was no breach. And this ignores any use value or salvage value of the new bagging system, which is the property of Lake River-though admittedly it also ignores the time value of money; Lake River paid $89,000 for that system before receiving any revenue from the contract.

To complete the picture, assume that the breach had not occurred till performance was 90 percent complete. Then the “liquidated damages” clause would not be so one-sided, but it would be one-sided. Carborundum would have paid $480,000 for bagging. Against this, Lake River would have incurred its fixed cost of $89,000 plus 90 percent of its variable costs of $337,000 or $303,000. Its total costs would thus be $392,000, and its net profit $88,000. But on top of this it would be entitled to “liquidated damages” of $53,000, for a total profit of $141,000-more than 30 percent more that its expected profit of $107,000 if there was no breach.

The reason for these results is that most of the costs to Lake River of performing the contract are saved if the contract is broken, and this saving is not reflected in the damage formula. As a result, at whatever point in the life of the contract a breach occurs, the damage formula gives Lake River more than its lost profits form the breach-dramatically more if the breach occurs at the beginning of the contract; tapering off at the end, it is true. Still, over the interval between the beginning of Lake River’s performance and nearly the end, the clause could be expected to generate profits ranging from 400 percent of the expected contract profits to 130 percent of those profits. And this is on the assumption that the bagging system has no value apart from the contract. If it were worth only $20,000 to Lake River, the range would be 434 percent to 150 percent.

Lake River argues that it would never get as much as the formula suggests, because it would be required to mitigate its damages. This is a dubious argument on several grounds. First, mitigation of damages is a doctrine of the law of court-assessed damages, while the point of a liquidated-damages clause is to substitute party assessment; and that point is blunted, and the certainty that liquidated-damages clauses are designed to give the process of assessing damages impaired, if a defendant can force the plaintiff to take less than the damages specified in the clause, on the ground that the plaintiff could have avoided some of them. It would seem therefore that the clause in this case should be read to eliminate any duty of mitigation, that what Lake River is doing is attempting to rewrite the clause to make it more reasonable, and that since actually the clause is designed to give Lake River the full damages it would incur from breach (and more) even if it made no effort to find a substitute use for the equipment that it brought to perform the contract, this is just one more piece of evidence that it is a penalty clause rather than a liquidated-damages clause. . . . But in any event mitigation would not mitigate the penal character of this clause.  If Carborundum did not ship the guaranteed minimum quantity, the reason was likely to be-the reason was-that the steel industry had fallen on hard times and the demand for Ferro Carbo was therefore down. In these circumstances Lake River would have little prospect of finding a substitute contract that would yield it significant profits to set off against the full contract price, which is the method by which it proposes to take account of mitigation. At argument Lake River suggested that it might at least have been able to sell the new bagging equipment to someone for something, and the figure $40,000 was proposed. If the breach occurred on the first day when performance under the contract was due and Lake River promptly sold the bagging equipment for $40,000, its liquidated damages would fall to $493,000. But by the same token its costs would fall to $49,000. Its profit would still be $444,000, which as we said was more than 400 percent of its expected profit on the contract. The penal component would be unaffected.

. . .

The fact that the damage formula is invalid does not deprive Lake River of a remedy. The parties did not contract explicitly with reference to the measure of damages if the agreed-on damage formula was invalidated, but all this means is that the victim of the breach is entitled to his common law damages. See, e.g., Restatement, Second, Contracts § 356, comment a (1981). In this case that would be the unpaid contract price of $241,000 minus the costs that Lake River saved by not having to complete the contract (the variable costs on the other 45 percent of the Ferro Carbo that it never had to bag). The case must be remanded to the district judge to fix these damages.. . .

The judgment of the district court is affirmed in part and reversed in part, and the case is returned to that court to redetermine both parties’ damages in accordance with the principles in this opinion. The parties may present additional evidence on remand, and shall bear their own costs in this court. Circuit Rule 18 shall not apple on remand.

AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.